Generate rolling look-ahead schedules for construction. Create 2-week, 3-week, or 6-week look-aheads with constraint analysis and crew coordination.

4.4k tokens
context cost
SKILL.md, read when the skill is used
3
files
plus reference files
0
copies elsewhere
how many repositories repackaged it
264
stars on the repo
on the repository, not the skill itself

Install

one command, takes just this skill from the repository
npx skills add https://github.com/datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill look-ahead-scheduler

The instruction itself

6 sections, as written by the author

Look-Ahead Scheduler

Overview

Generate rolling look-ahead schedules from the master schedule. Create actionable short-term plans with constraint analysis, crew assignments, and daily coordination.

> "Look-ahead planning catches 80% of schedule problems before they occur" — DDC Community

Look-Ahead Hierarchy

┌─────────────────────────────────────────────────────────────────┐
│                    LOOK-AHEAD PLANNING                           │
├─────────────────────────────────────────────────────────────────┤
│                                                                  │
│  Master Schedule (12+ months)                                    │
│       ↓                                                         │
│  Phase Schedule (3-6 months)                                    │
│       ↓                                                         │
│  6-Week Look-Ahead (make-ready)                                 │
│       ↓                                                         │
│  3-Week Look-Ahead (constraint removal)                         │
│       ↓                                                         │
│  Weekly Work Plan (commitment)                                  │
│       ↓                                                         │
│  Daily Coordination                                              │
│                                                                  │
└─────────────────────────────────────────────────────────────────┘

Technical Implementation

from dataclasses import dataclass, field
from typing import List, Dict, Optional, Set
from datetime import datetime, timedelta
from enum import Enum
from collections import defaultdict

class ConstraintType(Enum):
    PREDECESSOR = "predecessor"
    LABOR = "labor"
    MATERIAL = "material"
    EQUIPMENT = "equipment"
    INFORMATION = "information"
    PERMIT = "permit"
    INSPECTION = "inspection"
    SPACE = "space"
    WEATHER = "weather"

class ConstraintStatus(Enum):
    OPEN = "open"
    IN_PROGRESS = "in_progress"
    RESOLVED = "resolved"
    BLOCKED = "blocked"

class ActivityStatus(Enum):
    NOT_STARTED = "not_started"
    IN_PROGRESS = "in_progress"
    COMPLETE = "complete"
    DELAYED = "delayed"

@dataclass
class Constraint:
    id: str
    activity_id: str
    constraint_type: ConstraintType
    description: str
    responsible_party: str
    needed_by: datetime
    status: ConstraintStatus = ConstraintStatus.OPEN
    resolution_notes: str = ""
    resolved_date: Optional[datetime] = None

@dataclass
class LookAheadActivity:
    id: str
    name: str
    trade: str
    location: str
    planned_start: datetime
    planned_finish: datetime
    duration: int
    labor_hours: float
    crew_size: int
    predecessors: List[str] = field(default_factory=list)
    constraints: List[Constraint] = field(default_factory=list)
    status: ActivityStatus = ActivityStatus.NOT_STARTED
    percent_complete: float = 0.0
    notes: str = ""
    can_start: bool = False

@dataclass
class WeeklyWorkPlan:
    week_start: datetime
    week_end: datetime
    activities: List[LookAheadActivity]
    total_labor_hours: float
    trades_involved: List[str]
    constraints_to_resolve: List[Constraint]

@dataclass
class DailyPlan:
    date: datetime
    activities: List[LookAheadActivity]
    labor_by_trade: Dict[str, int]
    equipment_needed: List[str]
    inspections: List[str]
    safety_focus: str

class LookAheadScheduler:
    """Generate rolling look-ahead schedules."""

    def __init__(self, project_name: str):
        self.project_name = project_name
        self.activities: Dict[str, LookAheadActivity] = {}
        self.constraints: Dict[str, Constraint] = {}
        self.weekly_plans: List[WeeklyWorkPlan] = []

    def import_from_master(self, master_activities: List[Dict],
                          look_ahead_start: datetime,
                          look_ahead_weeks: int = 6) -> int:
        """Import activities from master schedule for look-ahead period."""
        look_ahead_end = look_ahead_start + timedelta(weeks=look_ahead_weeks)
        count = 0

        for act in master_activities:
            start = datetime.fromisoformat(act['planned_start']) if isinstance(act['planned_start'], str) else act['planned_start']
            finish = datetime.fromisoformat(act['planned_finish']) if isinstance(act['planned_finish'], str) else act['planned_finish']

            # Include if overlaps look-ahead period
            if start <= look_ahead_end and finish >= look_ahead_start:
                activity = LookAheadActivity(
                    id=act['id'],
                    name=act['name'],
                    trade=act.get('trade', ''),
                    location=act.get('location', ''),
                    planned_start=start,
                    planned_finish=finish,
                    duration=act.get('duration', (finish - start).days),
                    labor_hours=act.get('labor_hours', 0),
                    crew_size=act.get('crew_size', 0),
                    predecessors=act.get('predecessors', [])
                )
                self.activities[activity.id] = activity
                count += 1

        return count

    def add_constraint(self, activity_id: str, constraint_type: ConstraintType,
                      description: str, responsible_party: str,
                      needed_by: datetime) -> Constraint:
        """Add constraint to activity."""
        constraint_id = f"CON-{len(self.constraints)+1:04d}"

        constraint = Constraint(
            id=constraint_id,
            activity_id=activity_id,
            constraint_type=constraint_type,
            description=description,
            responsible_party=responsible_party,
            needed_by=needed_by
        )

        self.constraints[constraint_id] = constraint

        if activity_id in self.activities:
            self.activities[activity_id].constraints.append(constraint)

        return constraint

    def update_constraint(self, constraint_id: str, status: ConstraintStatus,
                         notes: str = "") -> Constraint:
        """Update constraint status."""
        if constraint_id not in self.constraints:
            raise ValueError(f"Constraint {constraint_id} not found")

        constraint = self.constraints[constraint_id]
        constraint.status = status
        constraint.resolution_notes = notes

        if status == ConstraintStatus.RESOLVED:
            constraint.resolved_date = datetime.now()

        return constraint

    def analyze_make_ready(self) -> Dict[str, List[str]]:
        """Analyze which activities are 'make-ready' (constraints resolved)."""
        ready = []
        not_ready = []
        blocked = []

        for act in self.activities.values():
            # Check predecessors complete
            pred_complete = all(
                self.activities.get(p, {}).status == ActivityStatus.COMPLETE
                for p in act.predecessors if p in self.activities
            )

            # Check constraints resolved
            open_constraints = [c for c in act.constraints
                              if c.status != ConstraintStatus.RESOLVED]

            if not pred_complete:
                blocked.append(act.id)
                act.can_start = False
            elif open_constraints:
                not_ready.append(act.id)
                act.can_start = False
            else:
                ready.append(act.id)
                act.can_start = True

        return {
            "ready": ready,
            "not_ready": not_ready,
            "blocked": blocked
        }

    def generate_weekly_plan(self, week_start: datetime) -> WeeklyWorkPlan:
        """Generate weekly work plan."""
        week_end = week_start + timedelta(days=6)

        # Get activities for this week
        week_activities = [
            act for act in self.activities.values()
            if act.planned_start <= week_end and act.planned_finish >= week_start
        ]

        # Calculate totals
        total_hours = sum(act.labor_hours for act in week_activities)
        trades = list(set(act.trade for act in week_activities if act.trade))

        # Get constraints needing resolution this week
        constraints_due = [
            c for c in self.constraints.values()
            if c.status == ConstraintStatus.OPEN and c.needed_by <= week_end
        ]

        plan = WeeklyWorkPlan(
            week_start=week_start,
            week_end=week_end,
            activities=week_activities,
            total_labor_hours=total_hours,
            trades_involved=trades,
            constraints_to_resolve=constraints_due
        )

        self.weekly_plans.append(plan)
        return plan

    def generate_daily_plan(self, date: datetime) -> DailyPlan:
        """Generate daily coordination plan."""
        # Get activities for this day
        day_activities = [
            act for act in self.activities.values()
            if act.planned_start <= date <= act.planned_finish
            and act.can_start
        ]

        # Labor by trade
        labor_by_trade = defaultdict(int)
        for act in day_activities:
            labor_by_trade[act.trade] += act.crew_size

        # Equipment needed
        equipment = []
        for act in day_activities:
            for c in act.constraints:
                if c.constraint_type == ConstraintType.EQUIPMENT:
                    equipment.append(c.description)

        # Inspections
        inspections = [
            c.description for c in self.constraints.values()
            if c.constraint_type == ConstraintType.INSPECTION
            and c.needed_by.date() == date.date()
        ]

        # Safety focus based on activities
        safety_focus = self._determine_safety_focus(day_activities)

        return DailyPlan(
            date=date,
            activities=day_activities,
            labor_by_trade=dict(labor_by_trade),
            equipment_needed=equipment,
            inspections=inspections,
            safety_focus=safety_focus
        )

    def _determine_safety_focus(self, activities: List[LookAheadActivity]) -> str:
        """Determine daily safety focus based on activities."""
        # Keywords to safety topics
        keywords = {
            "excavation": "Excavation Safety - Shoring, sloping, access",
            "steel": "Steel Erection - Fall protection, crane safety",
            "concrete": "Concrete Pour - Silica, formwork, PPE",
            "roof": "Fall Protection - 100% tie-off, guardrails",
            "electrical": "Electrical Safety - LOTO, qualified personnel",
            "crane": "Crane Safety - Rigging, load charts, signaling",
            "welding": "Hot Work - Fire watch, permits, ventilation"
        }

        for act in activities:
            name_lower = act.name.lower()
            for keyword, safety in keywords.items():
                if keyword in name_lower:
                    return safety

        return "General Site Safety - PPE, housekeeping, awareness"

    def generate_look_ahead_report(self, weeks: int = 3) -> str:
        """Generate look-ahead schedule report."""
        self.analyze_make_ready()
        today = datetime.now()

        lines = [
            f"# {weeks}-Week Look-Ahead Schedule",
            f"",
            f"**Project:** {self.project_name}",
            f"**Generated:** {today.strftime('%Y-%m-%d')}",
            f"**Period:** {today.strftime('%Y-%m-%d')} to {(today + timedelta(weeks=weeks)).strftime('%Y-%m-%d')}",
            f"",
        ]

        # Summary
        make_ready = self.analyze_make_ready()
        lines.extend([
            f"## Summary",
            f"",
            f"- **Total Activities:** {len(self.activities)}",
            f"- **Ready to Start:** {len(make_ready['ready'])}",
            f"- **Awaiting Constraints:** {len(make_ready['not_ready'])}",
            f"- **Blocked:** {len(make_ready['blocked'])}",
            f""
        ])

        # Open constraints
        open_constraints = [c for c in self.constraints.values()
                          if c.status == ConstraintStatus.OPEN]
        if open_constraints:
            lines.extend([
                f"## Open Constraints ({len(open_constraints)})",
                f"",
                f"| Activity | Type | Description | Responsible | Needed By |",
                f"|----------|------|-------------|-------------|-----------|"
            ])
            for c in sorted(open_constraints, key=lambda x: x.needed_by):
                lines.append(
                    f"| {c.activity_id} | {c.constraint_type.value} | {c.description} | "
                    f"{c.responsible_party} | {c.needed_by.strftime('%Y-%m-%d')} |"
                )
            lines.append("")

        # Weekly breakdown
        for week_num in range(weeks):
            week_start = today + timedelta(weeks=week_num)
            week_start = week_start - timedelta(days=week_start.weekday())  # Monday

            plan = self.generate_weekly_plan(week_start)

            lines.extend([
                f"## Week {week_num + 1}: {plan.week_start.strftime('%b %d')} - {plan.week_end.strftime('%b %d')}",
                f"",
                f"**Activities:** {len(plan.activities)} | **Labor:** {plan.total_labor_hours:.0f} hrs | **Trades:** {', '.join(plan.trades_involved)}",
                f""
            ])

            if plan.activities:
                lines.append("| Activity | Trade | Location | Start | Duration | Status |")
                lines.append("|----------|-------|----------|-------|----------|--------|")
                for act in sorted(plan.activities, key=lambda a: a.planned_start):
                    status = "Ready" if act.can_start else "Constraint"
                    lines.append(
                        f"| {act.name} | {act.trade} | {act.location} | "
                        f"{act.planned_start.strftime('%m/%d')} | {act.duration}d | {status} |"
                    )
                lines.append("")

        return "\n".join(lines)

    def get_constraint_log(self) -> str:
        """Generate constraint log."""
        lines = [
            "# Constraint Log",
            "",
            "| ID | Activity | Type | Description | Responsible | Status | Needed By |",
            "|----|----------|------|-------------|-------------|--------|-----------|"
        ]

        for c in sorted(self.constraints.values(), key=lambda x: x.needed_by):
            lines.append(
                f"| {c.id} | {c.activity_id} | {c.constraint_type.value} | "
                f"{c.description} | {c.responsible_party} | {c.status.value} | "
                f"{c.needed_by.strftime('%Y-%m-%d')} |"
            )

        return "\n".join(lines)

Quick Start

from datetime import datetime, timedelta

# Initialize scheduler
scheduler = LookAheadScheduler("Office Tower Construction")

# Import activities from master schedule
master_activities = [
    {
        "id": "A100",
        "name": "Level 5 MEP Rough-in",
        "trade": "Mechanical",
        "location": "Level 5",
        "planned_start": datetime.now(),
        "planned_finish": datetime.now() + timedelta(days=10),
        "labor_hours": 400,
        "crew_size": 5
    },
    {
        "id": "A101",
        "name": "Level 5 Framing",
        "trade": "Carpentry",
        "location": "Level 5",
        "planned_start": datetime.now() + timedelta(days=5),
        "planned_finish": datetime.now() + timedelta(days=15),
        "labor_hours": 320,
        "crew_size": 4,
        "predecessors": ["A100"]
    }
]

scheduler.import_from_master(master_activities, datetime.now(), look_ahead_weeks=6)

# Add constraints
scheduler.add_constraint(
    "A100",
    ConstraintType.MATERIAL,
    "Ductwork delivery",
    "ABC Mechanical",
    datetime.now() + timedelta(days=2)
)

scheduler.add_constraint(
    "A101",
    ConstraintType.INFORMATION,
    "Framing layout drawings",
    "Architect",
    datetime.now() + timedelta(days=4)
)

# Analyze make-ready status
status = scheduler.analyze_make_ready()
print(f"Ready: {len(status['ready'])}, Not Ready: {len(status['not_ready'])}")

# Generate look-ahead report
print(scheduler.generate_look_ahead_report(weeks=3))

# Generate daily plan
daily = scheduler.generate_daily_plan(datetime.now())
print(f"Today's safety focus: {daily.safety_focus}")

Requirements

pip install (no external dependencies)

Other skills for the same job

different authors, same section of the catalogue
Doc Coauthoring
by anthropics
vendor ×13

Guide users through a structured workflow for co-authoring documentation. Use when user wants to write documentation, proposals, technical specs, decision docs, or similar structured content. This workflow helps users efficiently transfer context, refine content through iteration, and verify the doc works for readers. Trigger when user mentions writing docs, creating proposals, drafting specs, or similar documentation tasks.

4k tokens
File Organizer
by frostant
×10

Intelligently organizes your files and folders across your computer by understanding context, finding duplicates, suggesting better structures, and automating cleanup tasks. Reduces cognitive load and keeps your digital workspace tidy without manual effort.

2.8k tokens
Domain Name Brainstormer
by frostant
×8

Generates creative domain name ideas for your project and checks availability across multiple TLDs (.com, .io, .dev, .ai, etc.). Saves hours of brainstorming and manual checking.

1.4k tokens
Brainstorming
by ZhanlinCui
×6

You MUST use this before any creative work - creating features, building components, adding functionality, or modifying behavior. Explores user intent, requirements and design before implementation.

626 tokens
Planning With Files
by ZhanlinCui
×5

Implements Manus-style file-based planning for complex tasks. Creates task_plan.md, findings.md, and progress.md. Use when starting complex multi-step tasks, research projects, or any task requiring >5 tool calls.

1.7k tokens scripts
Creating Financial Models
by anthropics
vendor ×3

This skill provides an advanced financial modeling suite with DCF analysis, sensitivity testing, Monte Carlo simulations, and scenario planning for investment decisions

1.3k tokens scripts
Scientific Brainstorming
by christophacham
×3

Creative research ideation and exploration. Use for open-ended brainstorming sessions, exploring interdisciplinary connections, challenging assumptions, or identifying research gaps. Best for early-stage research planning when you do not have specific observations yet. For formulating testable hypotheses from data use hypothesis-generation.

2.2k tokens
GitHub Project Management
by ComeOnOliver
×3

Comprehensive GitHub project management with swarm-coordinated issue tracking, project board automation, and sprint planning

7.1k tokens

How to use it

Copy the folder

Take datadrivenconstruction/look-ahead-scheduler from the repository into ~/.claude/skills for personal use, or into .claude/skills inside a project.

Check the name does not clash

The agent identifies a skill by the name field in its header. Two skills with the same name cannot sit side by side — one of them will be ignored.

Install what it needs

The instructions reference pip. Without those the skill loads but fails at the first command.