Change Order Analysis Agent Skill

Analyze and predict construction change orders using ML. Classify change order types, predict costs and schedule impacts, identify patterns, and optimize approval workflows.

5.3k tokens
context cost
SKILL.md, read when the skill is used
3
files
plus reference files
0
copies elsewhere
how many repositories repackaged it
264
stars on the repo
on the repository, not the skill itself

Install

one command, takes just this skill from the repository
npx skills add https://github.com/datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill change-order-analysis

The instruction itself

10 sections, as written by the author

Change Order Analysis

Overview

This skill implements machine learning-based change order analysis for construction projects. Predict change order costs, classify types, identify patterns in historical data, and streamline approval processes.

Capabilities:

  • Change order classification
  • Cost impact prediction
  • Schedule impact analysis
  • Pattern identification
  • Root cause analysis
  • Approval workflow optimization

Quick Start

from dataclasses import dataclass, field
from datetime import date, datetime
from typing import List, Dict, Optional
from enum import Enum

class ChangeOrderType(Enum):
    DESIGN_CHANGE = "design_change"
    OWNER_REQUEST = "owner_request"
    FIELD_CONDITION = "field_condition"
    CODE_COMPLIANCE = "code_compliance"
    VALUE_ENGINEERING = "value_engineering"
    ERROR_OMISSION = "error_omission"
    SCOPE_CHANGE = "scope_change"

class ChangeOrderStatus(Enum):
    DRAFT = "draft"
    SUBMITTED = "submitted"
    UNDER_REVIEW = "under_review"
    APPROVED = "approved"
    REJECTED = "rejected"
    IMPLEMENTED = "implemented"

@dataclass
class ChangeOrder:
    co_number: str
    title: str
    description: str
    co_type: ChangeOrderType
    status: ChangeOrderStatus
    submitted_date: date
    requested_by: str
    cost_impact: float
    schedule_impact_days: int
    affected_elements: List[str] = field(default_factory=list)

def classify_change_order(description: str) -> ChangeOrderType:
    """Simple rule-based classification"""
    description_lower = description.lower()

    if any(word in description_lower for word in ['design', 'drawing', 'specification']):
        return ChangeOrderType.DESIGN_CHANGE
    elif any(word in description_lower for word in ['owner', 'client', 'request']):
        return ChangeOrderType.OWNER_REQUEST
    elif any(word in description_lower for word in ['site', 'field', 'condition', 'unforeseen']):
        return ChangeOrderType.FIELD_CONDITION
    elif any(word in description_lower for word in ['code', 'regulation', 'compliance']):
        return ChangeOrderType.CODE_COMPLIANCE
    elif any(word in description_lower for word in ['value', 'alternative', 'savings']):
        return ChangeOrderType.VALUE_ENGINEERING
    elif any(word in description_lower for word in ['error', 'omission', 'mistake']):
        return ChangeOrderType.ERROR_OMISSION
    else:
        return ChangeOrderType.SCOPE_CHANGE

# Example
co = ChangeOrder(
    co_number="CO-001",
    title="Additional structural reinforcement",
    description="Site conditions revealed weaker soil requiring additional foundation reinforcement",
    co_type=classify_change_order("Site conditions revealed weaker soil"),
    status=ChangeOrderStatus.SUBMITTED,
    submitted_date=date.today(),
    requested_by="Site Engineer",
    cost_impact=50000,
    schedule_impact_days=5
)
print(f"CO Type: {co.co_type.value}")

Comprehensive Change Order System

Change Order Management

from dataclasses import dataclass, field
from datetime import date, datetime, timedelta
from typing import List, Dict, Optional, Tuple
from enum import Enum
import pandas as pd
import numpy as np

class ImpactSeverity(Enum):
    MINOR = "minor"  # < 1% cost, < 1 week schedule
    MODERATE = "moderate"  # 1-5% cost, 1-4 weeks schedule
    MAJOR = "major"  # 5-10% cost, 1-3 months schedule
    CRITICAL = "critical"  # > 10% cost, > 3 months schedule

@dataclass
class CostBreakdown:
    labor: float = 0
    materials: float = 0
    equipment: float = 0
    subcontractor: float = 0
    overhead: float = 0
    profit: float = 0

    @property
    def total(self) -> float:
        return self.labor + self.materials + self.equipment + self.subcontractor + self.overhead + self.profit

@dataclass
class ScheduleImpact:
    direct_days: int
    ripple_days: int
    critical_path_affected: bool
    affected_activities: List[str] = field(default_factory=list)

    @property
    def total_days(self) -> int:
        return self.direct_days + self.ripple_days

@dataclass
class ChangeOrderDetail:
    co_id: str
    co_number: str
    title: str
    description: str
    justification: str

    # Classification
    co_type: ChangeOrderType
    initiated_by: str  # owner, contractor, designer, etc.
    responsibility: str  # who pays

    # Status
    status: ChangeOrderStatus
    submitted_date: date
    approved_date: Optional[date] = None
    implemented_date: Optional[date] = None

    # Impact
    cost_breakdown: CostBreakdown = field(default_factory=CostBreakdown)
    schedule_impact: ScheduleImpact = None
    severity: ImpactSeverity = ImpactSeverity.MINOR

    # Affected scope
    affected_elements: List[str] = field(default_factory=list)
    affected_drawings: List[str] = field(default_factory=list)
    affected_specs: List[str] = field(default_factory=list)

    # Supporting documents
    attachments: List[str] = field(default_factory=list)
    related_rfis: List[str] = field(default_factory=list)
    related_cos: List[str] = field(default_factory=list)

    # Approval
    approvals: List[Dict] = field(default_factory=list)
    comments: List[Dict] = field(default_factory=list)

class ChangeOrderManager:
    """Manage project change orders"""

    def __init__(self, project_id: str, contract_value: float):
        self.project_id = project_id
        self.contract_value = contract_value
        self.change_orders: Dict[str, ChangeOrderDetail] = {}
        self.co_counter = 0

    def create_change_order(self, title: str, description: str,
                           co_type: ChangeOrderType,
                           initiated_by: str) -> ChangeOrderDetail:
        """Create new change order"""
        self.co_counter += 1
        co_id = f"CO-{self.project_id}-{self.co_counter:04d}"

        co = ChangeOrderDetail(
            co_id=co_id,
            co_number=f"CO-{self.co_counter:04d}",
            title=title,
            description=description,
            justification="",
            co_type=co_type,
            initiated_by=initiated_by,
            responsibility="TBD",
            status=ChangeOrderStatus.DRAFT,
            submitted_date=date.today()
        )

        self.change_orders[co_id] = co
        return co

    def update_cost(self, co_id: str, cost_breakdown: CostBreakdown):
        """Update change order cost"""
        co = self.change_orders.get(co_id)
        if co:
            co.cost_breakdown = cost_breakdown
            co.severity = self._calculate_severity(co)

    def update_schedule_impact(self, co_id: str, impact: ScheduleImpact):
        """Update schedule impact"""
        co = self.change_orders.get(co_id)
        if co:
            co.schedule_impact = impact
            co.severity = self._calculate_severity(co)

    def _calculate_severity(self, co: ChangeOrderDetail) -> ImpactSeverity:
        """Calculate change order severity"""
        cost_pct = co.cost_breakdown.total / self.contract_value * 100
        schedule_days = co.schedule_impact.total_days if co.schedule_impact else 0

        if cost_pct > 10 or schedule_days > 90:
            return ImpactSeverity.CRITICAL
        elif cost_pct > 5 or schedule_days > 30:
            return ImpactSeverity.MAJOR
        elif cost_pct > 1 or schedule_days > 7:
            return ImpactSeverity.MODERATE
        else:
            return ImpactSeverity.MINOR

    def submit_for_approval(self, co_id: str):
        """Submit change order for approval"""
        co = self.change_orders.get(co_id)
        if co and co.status == ChangeOrderStatus.DRAFT:
            co.status = ChangeOrderStatus.SUBMITTED
            co.submitted_date = date.today()

    def approve(self, co_id: str, approver: str, comments: str = ""):
        """Approve change order"""
        co = self.change_orders.get(co_id)
        if co:
            co.approvals.append({
                'approver': approver,
                'action': 'approved',
                'date': date.today().isoformat(),
                'comments': comments
            })
            co.status = ChangeOrderStatus.APPROVED
            co.approved_date = date.today()

    def get_summary(self) -> Dict:
        """Get change order summary"""
        if not self.change_orders:
            return {'message': 'No change orders'}

        total_cost = sum(co.cost_breakdown.total for co in self.change_orders.values())
        total_schedule = sum(
            co.schedule_impact.total_days if co.schedule_impact else 0
            for co in self.change_orders.values()
        )

        by_type = {}
        by_status = {}
        by_severity = {}

        for co in self.change_orders.values():
            t = co.co_type.value
            by_type[t] = by_type.get(t, 0) + co.cost_breakdown.total

            s = co.status.value
            by_status[s] = by_status.get(s, 0) + 1

            sev = co.severity.value
            by_severity[sev] = by_severity.get(sev, 0) + 1

        return {
            'total_change_orders': len(self.change_orders),
            'total_cost_impact': total_cost,
            'cost_impact_pct': total_cost / self.contract_value * 100,
            'total_schedule_impact_days': total_schedule,
            'by_type': by_type,
            'by_status': by_status,
            'by_severity': by_severity
        }

ML Classification and Prediction

from sklearn.ensemble import RandomForestClassifier, GradientBoostingRegressor
from sklearn.feature_extraction.text import TfidfVectorizer
from sklearn.model_selection import train_test_split
from sklearn.preprocessing import LabelEncoder
import pandas as pd
import numpy as np
import joblib

class ChangeOrderPredictor:
    """ML-based change order classification and cost prediction"""

    def __init__(self):
        self.type_classifier = None
        self.cost_predictor = None
        self.schedule_predictor = None
        self.vectorizer = TfidfVectorizer(max_features=500, ngram_range=(1, 2))
        self.type_encoder = LabelEncoder()
        self.is_trained = False

    def train(self, historical_data: pd.DataFrame):
        """Train models on historical change order data

        Expected columns:
        - description: text description
        - co_type: change order type
        - cost_impact: cost in dollars
        - schedule_impact: days of delay
        - contract_value: original contract value
        - project_phase: phase when CO was raised
        - affected_elements_count: number of affected elements
        """
        # Prepare text features
        text_features = self.vectorizer.fit_transform(historical_data['description'])

        # Prepare numeric features
        numeric_features = historical_data[[
            'contract_value', 'affected_elements_count'
        ]].values

        # Combine features
        X = np.hstack([text_features.toarray(), numeric_features])

        # Train type classifier
        y_type = self.type_encoder.fit_transform(historical_data['co_type'])
        X_train, X_test, y_train, y_test = train_test_split(X, y_type, test_size=0.2)

        self.type_classifier = RandomForestClassifier(n_estimators=100, random_state=42)
        self.type_classifier.fit(X_train, y_train)

        type_accuracy = self.type_classifier.score(X_test, y_test)

        # Train cost predictor
        y_cost = historical_data['cost_impact'].values
        self.cost_predictor = GradientBoostingRegressor(n_estimators=100, random_state=42)
        self.cost_predictor.fit(X, y_cost)

        # Train schedule predictor
        y_schedule = historical_data['schedule_impact'].values
        self.schedule_predictor = GradientBoostingRegressor(n_estimators=100, random_state=42)
        self.schedule_predictor.fit(X, y_schedule)

        self.is_trained = True

        return {
            'type_classifier_accuracy': type_accuracy,
            'models_trained': True
        }

    def predict(self, description: str, contract_value: float,
               affected_elements_count: int = 1) -> Dict:
        """Predict change order type and impacts"""
        if not self.is_trained:
            return {'error': 'Models not trained'}

        # Prepare features
        text_features = self.vectorizer.transform([description])
        numeric_features = np.array([[contract_value, affected_elements_count]])
        X = np.hstack([text_features.toarray(), numeric_features])

        # Predict type
        type_probs = self.type_classifier.predict_proba(X)[0]
        type_idx = np.argmax(type_probs)
        predicted_type = self.type_encoder.inverse_transform([type_idx])[0]

        # Predict cost
        predicted_cost = self.cost_predictor.predict(X)[0]

        # Predict schedule
        predicted_schedule = self.schedule_predictor.predict(X)[0]

        return {
            'predicted_type': predicted_type,
            'type_confidence': float(type_probs[type_idx]),
            'type_probabilities': {
                self.type_encoder.inverse_transform([i])[0]: float(p)
                for i, p in enumerate(type_probs)
            },
            'predicted_cost': float(max(0, predicted_cost)),
            'predicted_schedule_days': int(max(0, predicted_schedule)),
            'cost_as_pct_contract': float(predicted_cost / contract_value * 100)
        }

    def save_models(self, path: str):
        """Save trained models"""
        joblib.dump({
            'type_classifier': self.type_classifier,
            'cost_predictor': self.cost_predictor,
            'schedule_predictor': self.schedule_predictor,
            'vectorizer': self.vectorizer,
            'type_encoder': self.type_encoder
        }, path)

    def load_models(self, path: str):
        """Load trained models"""
        data = joblib.load(path)
        self.type_classifier = data['type_classifier']
        self.cost_predictor = data['cost_predictor']
        self.schedule_predictor = data['schedule_predictor']
        self.vectorizer = data['vectorizer']
        self.type_encoder = data['type_encoder']
        self.is_trained = True

Pattern Analysis

from collections import defaultdict
from typing import List, Dict
import pandas as pd

class ChangeOrderAnalyzer:
    """Analyze patterns in change orders"""

    def __init__(self, change_orders: List[ChangeOrderDetail]):
        self.cos = change_orders
        self.df = self._to_dataframe()

    def _to_dataframe(self) -> pd.DataFrame:
        """Convert change orders to DataFrame"""
        data = []
        for co in self.cos:
            data.append({
                'co_id': co.co_id,
                'co_type': co.co_type.value,
                'initiated_by': co.initiated_by,
                'cost': co.cost_breakdown.total,
                'schedule_days': co.schedule_impact.total_days if co.schedule_impact else 0,
                'submitted_date': co.submitted_date,
                'affected_elements': len(co.affected_elements),
                'severity': co.severity.value
            })
        return pd.DataFrame(data)

    def analyze_by_type(self) -> Dict:
        """Analyze change orders by type"""
        if self.df.empty:
            return {}

        analysis = {}
        for co_type in self.df['co_type'].unique():
            type_df = self.df[self.df['co_type'] == co_type]
            analysis[co_type] = {
                'count': len(type_df),
                'total_cost': type_df['cost'].sum(),
                'avg_cost': type_df['cost'].mean(),
                'total_schedule_days': type_df['schedule_days'].sum(),
                'avg_schedule_days': type_df['schedule_days'].mean()
            }

        return analysis

    def analyze_trends(self) -> Dict:
        """Analyze trends over time"""
        if self.df.empty:
            return {}

        self.df['month'] = pd.to_datetime(self.df['submitted_date']).dt.to_period('M')

        monthly = self.df.groupby('month').agg({
            'co_id': 'count',
            'cost': 'sum',
            'schedule_days': 'sum'
        }).rename(columns={'co_id': 'count'})

        return {
            'monthly_trend': monthly.to_dict(),
            'peak_month': monthly['count'].idxmax().strftime('%Y-%m'),
            'total_cost_trend': 'increasing' if monthly['cost'].is_monotonic_increasing else
                               'decreasing' if monthly['cost'].is_monotonic_decreasing else 'variable'
        }

    def identify_root_causes(self) -> List[Dict]:
        """Identify common root causes"""
        if self.df.empty:
            return []

        # Analyze by initiator and type combination
        causes = self.df.groupby(['initiated_by', 'co_type']).agg({
            'co_id': 'count',
            'cost': 'sum'
        }).reset_index()

        causes = causes.sort_values('cost', ascending=False)

        return [
            {
                'initiator': row['initiated_by'],
                'type': row['co_type'],
                'frequency': row['co_id'],
                'total_cost': row['cost'],
                'recommendation': self._get_recommendation(row['initiated_by'], row['co_type'])
            }
            for _, row in causes.head(10).iterrows()
        ]

    def _get_recommendation(self, initiator: str, co_type: str) -> str:
        """Generate recommendation based on pattern"""
        recommendations = {
            ('designer', 'design_change'): 'Improve design review process and BIM coordination',
            ('designer', 'error_omission'): 'Implement design quality checks and clash detection',
            ('owner', 'owner_request'): 'Define scope more clearly during planning phase',
            ('owner', 'scope_change'): 'Conduct thorough requirements gathering',
            ('contractor', 'field_condition'): 'Enhance site investigation before construction',
            ('contractor', 'value_engineering'): 'Include VE sessions earlier in project'
        }

        return recommendations.get(
            (initiator.lower(), co_type),
            'Review process and implement preventive measures'
        )

    def calculate_risk_score(self) -> float:
        """Calculate overall change order risk score"""
        if self.df.empty:
            return 0

        # Factors:
        # - Frequency of COs
        # - Cost impact severity
        # - Schedule impact severity
        # - Trend direction

        co_rate = len(self.df) / 12  # COs per month (assuming 12 month project)
        avg_cost_impact = self.df['cost'].mean()
        avg_schedule_impact = self.df['schedule_days'].mean()

        # Normalize and weight
        freq_score = min(1, co_rate / 10) * 30  # Up to 30 points
        cost_score = min(1, avg_cost_impact / 50000) * 40  # Up to 40 points
        schedule_score = min(1, avg_schedule_impact / 30) * 30  # Up to 30 points

        return freq_score + cost_score + schedule_score

    def generate_report(self, output_path: str) -> str:
        """Generate comprehensive analysis report"""
        with pd.ExcelWriter(output_path, engine='openpyxl') as writer:
            # Summary
            summary = pd.DataFrame([{
                'Total COs': len(self.cos),
                'Total Cost Impact': self.df['cost'].sum(),
                'Total Schedule Impact (days)': self.df['schedule_days'].sum(),
                'Risk Score': self.calculate_risk_score()
            }])
            summary.to_excel(writer, sheet_name='Summary', index=False)

            # By type
            pd.DataFrame(self.analyze_by_type()).T.to_excel(
                writer, sheet_name='By_Type'
            )

            # Root causes
            pd.DataFrame(self.identify_root_causes()).to_excel(
                writer, sheet_name='Root_Causes', index=False
            )

            # All COs
            self.df.to_excel(writer, sheet_name='All_COs', index=False)

        return output_path

Quick Reference

| CO Type | Typical Cause | Prevention Strategy |

|---------|--------------|---------------------|

| Design Change | Incomplete design | BIM coordination, design reviews |

| Owner Request | Changing requirements | Clear scope definition |

| Field Condition | Unforeseen site issues | Thorough site investigation |

| Code Compliance | Regulation changes | Early code review |

| Value Engineering | Cost savings opportunity | VE workshops |

| Error/Omission | Design mistakes | QA/QC processes |

Resources

  • AIA A201: General Conditions of the Contract
  • AGC ConsensusDocs: Change order management
  • DDC Website: https://datadrivenconstruction.io

Next Steps

  • See document-classification-nlp for CO document processing
  • See risk-assessment-ml for project risk analysis
  • See cost-prediction for cost estimation

Other skills for the same job

different authors, same section of the catalogue
Doc Coauthoring
by anthropics
vendor ×13

Guide users through a structured workflow for co-authoring documentation. Use when user wants to write documentation, proposals, technical specs, decision docs, or similar structured content. This workflow helps users efficiently transfer context, refine content through iteration, and verify the doc works for readers. Trigger when user mentions writing docs, creating proposals, drafting specs, or similar documentation tasks.

4k tokens
File Organizer
by frostant
×10

Intelligently organizes your files and folders across your computer by understanding context, finding duplicates, suggesting better structures, and automating cleanup tasks. Reduces cognitive load and keeps your digital workspace tidy without manual effort.

2.8k tokens
Domain Name Brainstormer
by frostant
×8

Generates creative domain name ideas for your project and checks availability across multiple TLDs (.com, .io, .dev, .ai, etc.). Saves hours of brainstorming and manual checking.

1.4k tokens
Brainstorming
by ZhanlinCui
×6

You MUST use this before any creative work - creating features, building components, adding functionality, or modifying behavior. Explores user intent, requirements and design before implementation.

626 tokens
Planning With Files
by ZhanlinCui
×5

Implements Manus-style file-based planning for complex tasks. Creates task_plan.md, findings.md, and progress.md. Use when starting complex multi-step tasks, research projects, or any task requiring >5 tool calls.

1.7k tokens scripts
Creating Financial Models
by anthropics
vendor ×3

This skill provides an advanced financial modeling suite with DCF analysis, sensitivity testing, Monte Carlo simulations, and scenario planning for investment decisions

1.3k tokens scripts
Scientific Brainstorming
by christophacham
×3

Creative research ideation and exploration. Use for open-ended brainstorming sessions, exploring interdisciplinary connections, challenging assumptions, or identifying research gaps. Best for early-stage research planning when you do not have specific observations yet. For formulating testable hypotheses from data use hypothesis-generation.

2.2k tokens
GitHub Project Management
by ComeOnOliver
×3

Comprehensive GitHub project management with swarm-coordinated issue tracking, project board automation, and sprint planning

7.1k tokens

How to use it

Copy the folder

Take datadrivenconstruction/change-order-analysis from the repository into ~/.claude/skills for personal use, or into .claude/skills inside a project.